← Back to Project StoriesAbout this project
The Brew Creek Centre
Whistler, BC
Installed March 2022
Features
Installation
EcoBridge Landscape



01 / The setting & foundation
At The Brew Creek Centre in Whistler, this patio was built over an irregular bedrock surface in March 2022. Sheet-metal edging enclosed the area so the base could be built up and levelled to support the new natural stone paving.
The irregular basalt pieces were substantial: approximately three inches thick and around two feet wide. A large section of exposed bedrock was retained, with the patio shaped around it to preserve the character of the surrounding landscape.
Drainage was a priority for the client. To accommodate the changing bedrock levels, we used a base of ¾-inch clear crushed rock, approximately 18 inches deep in some areas and seven inches in others.
02 / The challenges & craftsmanship
Rain and temperature made the resin work particularly demanding. A commercial tent was rented to keep rain out of the working area, with heaters maintaining suitable installation conditions from early morning through the evening.
Access added another challenge. A small machine could transport materials only part of the way; the remaining distance required the team to carry the heavy materials by hand. Their care and effort were essential to completing the installation.
Once the basalt pieces were positioned, each individual stone was covered to prevent staining from the resin. Rainbow pebbles filled the spaces around the stones and were bonded with a specialist German resin, creating a stable pebble finish while allowing drainage through the joints.
The pebble colours were chosen to complement the cabins, helping the patio feel like an extension of the buildings. Attention to the smallest details—from the stone protection to the transitions around the bedrock—gave the finished work its character.
03 / The finished patio
The finished patio brings together irregular basalt, colourful bonded pebbles and the original bedrock. Its materials echo the cabins while the retained rock keeps the surrounding landscape at the heart of the composition.
EcoBridge was honoured to carry out this installation at The Brew Creek Centre. It reflects the care we bring to every project: practical problem-solving, careful execution and attention to the smallest details.





Explore related work